Monday, 12 December 2016

Production schedule




Wk. 1
Mon 31th Oct
Tues 1st Nov
Weds  2nd Nov
Thurs 3rd Nov
Fri 4th Nov
Sat 5th Nov
Sun 6th

The group have a meeting and are given out set roles
In the tv studio, we discussed set up and who is doing what role
Beginning blog post/journals of the process
start blogging journals



Wk. 2
Mon 7th Nov
Tues 8th Nov
Weds 9th Nov
Thurs 10th Nov
Fri 11th Nov
Sat 12th Nov
Sun 13th Nov




Evaluating the tv studio and learning how to use the different types of equipment
Group practice runs with the equipment
Finding resolution to issues with cameras and technical equipment




Wk. 3
Mon 14th Nov
Tues 15th Nov
Weds 16th Nov
Thurs 17th Nov
Fri 18th Nov
Sat 19th Nov
Sun 20th Nov


Reece




Images
Hazard
    C:\Users\s1500021\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Word\IMG_9695.jpg
The location for this is in the control room of the studio. The possible hazards for this are wires being tangled up which could cause people to trip.


C:\Users\s1500021\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Word\IMG_9699.jpg
The location for this is the TV studio. There could be a few hazards when approaching the doors because it’s quite narrow and there’s a bin on the left side which could cause someone to trip if they’re running or walking fast.


IMG_9700
The location for this is inside the TV studio. As it is quite particularly big it could cause obstruction. Also the heat from the light could be a hazard too.




IMG_9685
These cameras are based in the TV Studio. As they are quite big and hefty to move, this could cause a hazard to occur. Also it has many wires all over the place so people tripping over them would be a big hazard risk.



IMG_9681
These tables are right back in the middle of the TV studio. They are next to the exit so this could cause people to trip over and also cause objects to trip over.





Images
Hazard
    C:\Users\s1500021\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Word\IMG_9695.jpg
The location for this is in the control room of the studio. The possible hazards for this are wires being tangled up which could cause people to trip.


C:\Users\s1500021\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Word\IMG_9699.jpg
The location for this is the TV studio. There could be a few hazards when approaching the doors because it’s quite narrow and there’s a bin on the left side which could cause someone to trip if they’re running or walking fast.


IMG_9700
The location for this is inside the TV studio. As it is quite particularly big it could cause obstruction. Also the heat from the light could be a hazard too.




IMG_9685
These cameras are based in the TV Studio. As they are quite big and hefty to move, this could cause a hazard to occur. Also it has many wires all over the place so people tripping over them would be a big hazard risk.



IMG_9681
These tables are right back in the middle of the TV studio. They are next to the exit so this could cause people to trip over and also cause objects to trip over.

    IMG_9691
This computer is located in the Control room, there are many wires in this picture which is a hazard. The room is quite packed with lots of equipment and gear. So if there are more people in each station than there are meant to be, this will cause a hazard.

   

IMG_9694



The switchboard is located in the control room. The switchboard is based right in the left corner. This is very packed and tight, if it is over packed there could be a hazard

IMG_9688
The sound board is located in the control room, beside the soundboard are other pieces of equipment. This means there are lots of wires all over the place which is prone to a hazard.




IMG_9687
The plug switch is based right in the middle left of the TV Studio. It goes all the way to the back right of the room. So there are lots of wires on the floor which could cause people and/or objects to trip.


IMG_9693
This is the main power switches for the studio which is based right in the corner of the control room. The space between this and the switchboard is very thin so this could cause a hazard because it could get overly packed and could cause a hazard.




Meetings


Date & Time
Discussion and Topic of the meeting
Week 1 -31/10/16 10:20am






This was our first meeting as a group. We discussed what the content of the show was and how we can set up the TV room for it. Overall, we plan what each role was and what had to be done for it.
Sourced from Keeley’s Blogger
my idea is to use social media to create a game show, there will be two teams of three and each team will compete to create funny and creative images and videos using social sites such as snapchat, tumblr and music.ly. the ages will range from 15-25 and the watershed will be from 9:30pm.
Week 2 - 02/11/16 10:20am
We had our second meeting where we discuss our TV show and the different types of close we can use and includes in our show. For an example,we liked the idea of having close up of the iPad in the show and most likely we will need to pre-record these clips and insert them on the production day.
Week 3 -7/11/16 11.40am
This week we decided as a group to give out individu
al task.
Dani - Props list and set design( Including logos) & Secondary  Research Evidence
Berfin - Budget & Regular Production Meeting (Regular blog post), Reece, Logo
Keeley- Primary Research Evidence , script
Victor -   Shooting- Camera Script, Equipment checklist , Reece
Maarya- Storyboard & Risk assessments
Chai-ann- Production Schedule & Shooting- Camera Script
Timi -Linking and inserts, script
Zak- Shot list, Studio floor plans, Logo
Abigail - Production Schedule, Lighting Plan
Week 4 - 09/11/16 11.10am
Today we discuss the main part of the pre-production as we had a deadline on the 14th of November. Everyone team member given a little update where they were on the pre-production.
Storyboard
Equipment check
Research evidence
Location recce








Week 5 - 14/11/16 9:00am
This morning we discussed what was complete for the pre-production.For an example, Berfin, Victor, Zak and Maarya was done with their individual task and started to work with other. Another example, Berfin is starting and designing the logo with Zak.
Complete Pre-production
Berfin  - Budget & Reece
Victor - Equipment & Reece
Maarya - Storyboard
Zak - Studio Floor Plan
Week 6 - 15/11/16 10:20am
In this reporting meeting, we spoke about what had to be done and when.
Tasks that needs to be completed
Dani - Props list and set design( Including logos) & Secondary Research Evidence
Keeley- Primary Research Evidence , script
Victor -   Shooting- Camera Script
Chai-ann- Production Schedule & Shooting- Camera Script
Timi - Linking and inserts, script
Zak- Shot list, Logo
Abigail - Production Schedule, Lighting Plan
Week 7 - 28/11/16 9:00am
This morning as a group we discussed deadlines and how it could be complete by Wednesday 30th . Berfin asked anyone who needed help or support with their pre-production and distributed any work between Victor, Maarya and Berfin as they are done.
Lighting Plan - Berfin
Set Design & Proplist - Dani
Secondary Research - Dani
Week 8 - 07/12/16 11:40am

Finally, the script has been completed so as group we read and discussed the script and the error that has been made. As the script was really short half of the team was confused so we decided to make a point system and finalised the three games included in the show. We also discussed our job roles in the production.

Director -  Dani
Vision Mixer - Berfin
Floor Manager - Maarya
Cam 1 - Timi
Cam 2 (Main)- Vic
Cam 3 - Abi
Sound - Zak
Lighting - Chai ann
Tech/Monitor - Keeley

System Point - By Likes on social media
Three games - Memes, Musically, Snapchat Filter.
Week 9 - 12/12/16 9:00am




Lighting plan




Lighting plan                                            Abigail Mbaki




*Black out *
Front lights fade in (5 AND 6) in and is on the host (use low key light)
Host introduces himself/herself …….

Host introduces the guest …….
After induction
light s 5 & 6 fade down
Lights 1&2 on when host introduces them
Then lights 3&4 on when guest introduces them

Host: both teams will be competing to see who has the better social thumb…………
* All studio lights turn on * (lights 1,2,3,4,,5 and 6)

Host : The first game is called meme generator ….
Host : are you ready ?

*dim down front lights 5 & 6*

Teams respond

Host: Here is your first image ………..
(image comes on screen)
*dim down lights  for 15 seconds 1,2,,3,and 4 so we can see the image
*after 15 seconds put back lights 1,2,3,4

Host:



Equipment Checklist





Equipment checklist:


  • 2 iPad ( 1 for extra)
  • 3 cameras
  • Lighting
  • Sound
  • Tv Monitor
  • Applications (Snapchat, Instagram, Twitter)
  • Tripods
  • Control room
  • Recco Live


 


Equipment
Where it will be used?
Cost?
2 iPad
It will be used on the table
£300
3 cameras
Instead of using the cameras that broke down, we are going to use our iPads because our cameras broke down.
 
£15k-20k
Lighting
The lighting will be used In the studio
£2k
Sound
The sound will be in the control room
£5k
TV Monitor
The TV monitor is based in the control room.
 
Applications (Snapchat, Instagram, Twitter)
The applications are located on the iPads
Free
Tripods
The tripods will be located in the same positions as the cameras as well be placing the ipads on tripods.
£300-700
Control room
The control room is based behind the studio.
n/a
Recco live
We will use this application as a vision mixer as our main cameras went down. So our ipads are our substitutes.
$5